Anthropic's 2028 Power Mix Estimated at 87% Gas, 11% Coal

On November 16, nonprofit Better Data Center Project published a case study estimating that Anthropic's contracted US data centers will run on 87% natural gas and 11% coal in 2028, with annual CO2 emissions of 17 to 38 million tonnes and a mid-case of 32 million tonnes.

Aerial view of a data center campus with power infrastructure under a clear sky
AI-generated illustration

What happened

The group tracked 15 GW of compute Anthropic had contracted as of October 2026, with 5.9 to 9.6 GW tied to identified sites, then used the US EPA's AVERT tool to model which power plants would serve the added load, producing the power mix and emissions range.

The analysis also finds Anthropic has made no direct renewable energy commitments or investments in the US, with its only publicly disclosed renewable projects in Norway and Canada, while it has bought commitments for 1.7 GW of heavy-duty gas generators for $3.4 billion.

Key facts

  1. Mix: Estimated 2028 power mix: about 87% gas and 11% coal, on a marginal-generator basis
  2. Scale: 15 GW of compute contracted as of October 2026, with 5.9–9.6 GW tied to identified sites
  3. Emissions: Estimated annual CO2 of 17–38 million tonnes, mid-case 32 million tonnes, above California power sector emissions of 31.1 million tonnes in 2024
  4. On-site power: About 2.5 GW from on-site gas generation, 80% of it simple-cycle turbines and engines
  5. Carbon intensity: Estimated average carbon intensity of 1,033–1,076 lb CO2e per MWh, about 35% above the US grid average
  6. Method: Based on the EPA AVERT tool modeling marginal generators; assumes PUE of 1.1–1.2 and utilization of 60%–80%; figures are estimates, not measurements
  7. Company position: Anthropic published its approach to responsible data center development in October 2026, saying it follows air permitting processes and requires emissions controls at power plants

Why it matters

Anthropic listed on Nasdaq on November 19, and this is the first site-by-site estimate of the energy mix behind its compute buildout, putting figures of 87% gas and 11% coal on a fossil-dominated power mix.
Useful Tap if this story helped you
Send to a friendMakes a share image for X, WeChat, Telegram and more

SourcesBetter Data Center Project (Nov 16, 2026); DEV Community (Nov 22, 2026). This article is compiled from public information and does not constitute investment advice.

From HIMIAO Horizon · himiao.ai

Grab todayAdobe Creative Cloud Pro: 57% off first yearHIMIAO Picks →

Follow HIMIAO Horizon

No sign-up · Unsubscribe any time

Email

Notifications

A ping on your phone or computer when the brief is out. No email needed.

HIMIAO PicksWeekly freebies: one email every Friday, a 5-minute read

Comments

  1. Loading comments…
Ask the cat